ECoR GM Inspects Boudh-Purunakatak Rail Section of Khurda Road-Balangir Rail Line Project
by Argus News
Sun, Nov 10 | 9:02 p.m.

Bhubaneswar, Nov 10: General Manager of East Coast Railway (ECoR), Parmeshwar Funkwal, has inspected the newly constructed rail line between Boudh and Purunakatak to review progress in the ongoing Khurda Road-Balangir Rail Line project. 

Key Highlights from the Inspection:
•    Progress of Track laying: The engine rolling and testing for the track between Boudh and Purunakatak has already been successfully completed by the Construction Unit.
•    Project Completion: Out of the total 301 km stretch of the Khurda Road-Balangir Rail Line, 226 km has been completed to date, with 199 km already commissioned and fit for operations.
•    Progress on New Section: A significant milestone was achieved with the completion of a 27 km stretch between Purunakatak and Boudh. In the newly constructed stretch between Purunakatak and Champapur includes 9 major bridges, 2 Road Over Bridges (ROBs), 15 Road Under Bridges (RUBs), and 35 minor bridges, all essential for facilitating safe and efficient rail operations.
•    Ongoing Construction Efforts: The rail line from Boudh to Champapur, part of the larger stretch, was completed in May 2024, and construction activities are now progressing rapidly in the remaining sections. To expedite the completion, work is being carried out from both ends simultaneously, ensuring adherence to the project's ambitious timeline.
•    Remaining Section: Of the total 301 km, the remaining 75 km section between Purunakatak and Daspalla, which includes tunnel construction through dense jungle and sanctuary areas, is progressing steadily. The completion of these tunnels is expected to be a major breakthrough for the project.

Funkwal, during his inspection, emphasized the importance of maintaining the pace of construction and ensuring that necessary passenger amenities are in place at all the proposed stations. He further expressed confidence that the project will be completed on time, despite the engineering challenges posed by the difficult terrain, particularly the tunnel sections.

As the project continues to progress, the Khurda Road-Balangir Rail Line remains a key initiative for enhancing connectivity and creating new opportunities for economic development across Odisha.

PM NARENDRA MODI
PM Modi To Participate In ‘Odisha Parba 2024’ Tomorrow
New Delhi, Nov 23: Prime Minister Narendra Modi will participate in the ‘Odisha Parba 2024’ programme in New Delhi tomorrow, informed Prime
ASSEMBLY POLLS
'Second Innings': BJP-led Mahayuti scripts history with Maha landslide, JMM retains Jharkhand
Mumbai/Ranchi, Nov 23: The BJP-led Mahayuti stormed back to power in Maharashtra with a historic landslide that saw it on course to get over 230 seats in the
FOOTBALL
Santosh Trophy: Odisha Rout Chhattisgarh To Make Final Rounds
Amritsar, Nov 23: Odisha qualified for the final rounds of the 78th National Football Championship for the Santosh Trophy from Group F qualifiers when they
ASSEMBLY POLLS
Mahayuti Scores Landslide Victory In Maharashtra, JMM-led Alliance Leads In Jharkhand
New Delhi, Nov 23: The ruling Mahayuti alliance won the Maharashtra assembly polls and is poised for a landslide mandate with JMM-led alliance slated to
CRICKET
BGT 2024-25: Jaiswal, Rahul Help India Seize Control Over Australia; Push Lead To 218
Perth, Nov 23: After a fast-moving opening day which saw 17 wickets fall in 76.4 overs, many expected Day Two of the first Test to follow the same route. But